Development projects in Norra Djurgårdsstaden

Norra Djurgårdsstaden is one of Europe's largest urban development areas: 236 hectares where 12,000 homes and 35,000 workplaces are being built into the 2030s. This page covers what is under construction now, which phases lie ahead, and which of Gasverket's industrial buildings have already reopened with a new use.

Everything here is read from the City of Stockholm's own pages, and each section shows when it was last checked. The page covers Hjorthagen and Gasverket — the same area as the rest of the directory.

Hectares
236
New homes
12,000
New workplaces
35,000

Under way and coming

Individual buildings with a published timetable. The links go to the city's own project pages.

Hus 10, Reningshus II
Offices · Gasverket
The Royal Swedish Opera

The 1905 purification house has been rebuilt as offices, and in autumn 2026 the Royal Swedish Opera takes the premises over from Sandvik, who moved in as the first tenant in 2020. The building was designed by Hjalmar Westlund, and the conversion was not allowed to show in the facade: steel window frames, cast-iron roof trusses and an overhead crane are preserved and reused.

Autumn 2026● Opening soon
Gasklocka 2, Gasometer
Culture · Gasverket
City of Stockholm, operated by Miramis

Ferdinand Boberg’s 1899 gasholder becomes the culture and events venue Gasometer. Because the building carries Stockholm’s strongest heritage classification, the stage is built as a free-standing house inside the old brick shell — 25 metres high and 40 metres wide, designed by Jan Izikowitz at Tengbom. Eleven floors, eight of them public, and 1,560 seats. The city owns the building, Miramis runs the venue, and the Royal Swedish Opera is the first tenant, using Gasometer as its main stage from 2027 to 2030.

Opens spring 2027● Under construction
Gasklocka 1
Hotel · Gasverket

The smaller of Gasverket’s two brick gasholders is being converted into a hotel, work that started in autumn 2024. Gasklocka 1 belongs to the gasworks’ first construction stage and went into service in autumn 1893. It is a wet-seal holder, where the gas was enclosed in a vessel with a water seal, and one of the buildings on the site best preserved from its own era.

Work started autumn 2024● Under construction
Kolarlunden och Hagelbössan
Park · Hjorthagen
Norra innerstaden district administration

Two small parks in old Hjorthagen are being upgraded during 2026, following a citizen’s proposal and a consultation with older residents of the district. Kolarlunden, at the corner of Kolargatan and Artemisgatan, gets a boules court, renewed paths and seating, and mown lawn is gradually being turned into meadow. The park in the Hagelbössan block is renewed in the autumn with a new path, lighting, seating and a frame of shrubs and trees.

During 2026● Under construction
Gasklocka 5
Offices · Gasverket

The spherical high-pressure holder from the 1970s is planned to be rebuilt as offices. The shape was typical of its time and common worldwide, and it differs completely from the two brick gasholders next to it. No timetable for the conversion has been published.

○ Planned
Hjorthagsgaraget
Infrastructure · Hjorthagsberget
Stockholm Parkering

An existing rock cavern in Hjorthagsberget is to be rebuilt as a car park with up to 1,000 spaces, mainly for residents and businesses in Gasverket, Kolkajen and Ropsten. The point is to meet the parking need without putting more cars on the streets. The detailed plan came into force on 18 November 2018; Stockholm Parkering will own, build and operate the garage. No construction start date has been published.

Detailed plan in force since 2018○ Planned

Phases

The city's own timetable for Hjorthagen, with construction start, occupancy and home counts. Completed phases come last.

Gasverket
2015–2032

West: start 2015, occupancy 2019–2027. East: start 2025, occupancy 2026–2032

CA Fastigheter, Åke Sundvall, SISAB, Klätterverket, Spårvägsmuseet, the city property office

Around 200 homes in the eastern part● Under construction
Gasklocka 3 och 4
2025–2029

Excavation and remediation 2026, start 2027, occupancy 2029

Obos

Around 360 homes● Under construction
Starkströmmen
2027–2029

Offices and an operations depot can start at the earliest in 2027, occupancy 2029

Elementica, Vasakronan, Trafikverket

○ Planned
Ängsbotten
2027–2031

Start at the earliest 2027, occupancy 2029–2031

Wallenstam, Primula Byggnads, Aros Bostadsutveckling, NREP

400 homes○ Planned
Hjorthagskransen
2028–2032

Plan adopted at the earliest 2028, start at the earliest 2030, occupancy at the earliest 2032

Erik Wallin, Arwidsro Fastigheter, Djurgårdens Elitfotboll (new club offices by Hjorthagens IP)

Around 150–200 homes○ Planned
Elektriciteten
2030–2032

Housing starts 2030, occupancy 2032. The switchgear station started in 2021

Ellevio, Klövern

Around 150–200 homes○ Planned
Kolkajen
2032–

Start at the earliest 2032, occupancy at the earliest 2033

Ten developers, among them Stockholmshem, Obos Kärnhem, Åke Sundvall and Selvaag

1,300 homes and two preschools○ Planned
Ropsten

Construction start under study

Under study○ Planned
Norra 1
2011–2014

Start 2011, occupancy 2012–2014

670 homes○ Completed
Västra
2012–2017

Start 2012, occupancy 2014–2017

1,250 homes○ Completed
Norra 2
2014–2017

Start 2014, occupancy 2016–2017

600 homes○ Completed
Brofästet
2016–2020

Start 2016, occupancy 2018–2020

600 homes○ Completed
Jackproppen
2019–2022

Start 2019, occupancy 2022

Erik Wallin

54 homes○ Completed

Source: City of Stockholm (vaxer.stockholm) · the city's page updated 2026-05-29

The development project also covers Värtahamnen, Frihamnen, Loudden, and Energihamnen, which lie outside the area this directory covers. The whole project at the City of Stockholm

Already open in Gasverket

Industrial buildings that have been renovated and reopened with a new use. Several of them are in the directory.

Hus 27, Ångpannehus — Renovated — Gasverket’s smallest building
Ferdinand Boberg, 1893 · new use 2024
Hus 9, Regenerationshus — Spårvägsmuseet tram museum
In the directory:Spårvägsmuseet
Ferdinand Boberg, 1892, extended 1915 · new use 2022
Hus 14, Verkstadshus — Restaurant O.C.R.A. and Granero Bakery
In the directory:O.C.R.A. · Granero Bakery
Ferdinand Boberg, 1893 · new use 2022
Bobergstorget — The area’s square, with seating and a water mirror
Sweco and Nola Industrier, laid out 2022 · new use 2022
Hus 8, Reningshuset — Berghs School of Communication
Ferdinand Boberg, 1905 · new use 2021
Hus 11, Förrådshus I — Förskolan Anna preschool
A.R., 1909 · new use 2021
Hus 7, Mätarhuset — Klätterverket climbing centre and Matkafé Mätarhuset
Ferdinand Boberg, 1893 · new use 2019
Hus 20, Maskinhus — Systembolaget
Åke Tengelin, 1937–1938 · new use 2019
Hus 13, Verkstadshus II — Bobergsskolan, with room for 900 children
Hjalmar Westerlund, 1910 · new use 2019
Hus K, Hjorthagshallen — Sports hall with a gym and a fencing room
AIX, new build 2019 · new use 2019

Source: Norra Djurgårdsstaden 2030 (City of Stockholm)

Every fact checked against the city's own pages on 2026-07-30 or later